Wednesday, October 20, 2010
Sunday, October 3, 2010
New Renovation shows great progress
Friday, September 17, 2010
Wednesday, September 1, 2010
Saturday, August 21, 2010
Thursday, August 19, 2010
Tuesday, August 10, 2010
Monday, August 9, 2010
Monday, February 23, 2009
Construction Progress
The Library also has plans to restore the historic entrance to the Carnegie building in May/June 2009. The current two sets of aluminum doors will be replaced with new exterior wood & glass paneled doors and interior french doors that will match the original door design of 1903. The vestibule will be pushed out about 1 1/2 feet and the front steps will be reconstructed to bring them in compliance with current building codes.
Here are some pictures of the interior construction progress.
Upper Level Adult Reading Area

Main Level Children's Room with fun curved ceilings & story hour room.

The Cellar showing some of the HVAC system that is tied into the geothermal system
Monday, December 15, 2008
December Update
The construction team is currently in the process of enclosing the building. The gutters are being hung, the glass is being set in the window frames, and the exterior stone veneer is being installed. Once these have been accomplished and the exterior sealed, interior work will explode with activity. We cannot wait for the public to survey the spectacular views from the two upper levels looking over the majestic Hudson River, the eastern shoreline in the distance, and the Tappan Zee Bridge.
Below are floor plans of the new and expanded Library – a sneak preview for those lucky enough to visit this web page. The Computer Resource Center is still under development, so the design shown is not complete. In fact, these plans continue to be tweaked and improved upon as the building goes up. You can click on these plans and see a larger view to better see the details.
Stephen Hoefer, MBA
Manager of Operations & Finance
845-358-3370 x33



Friday, August 1, 2008
Geothermal Installation to begin
The geothermal system will use much less energy, does not burn fossil fuels, does not produce pollution, and is estimated to save the Library $30,000 a year in heating and cooling costs for the life of the system. Even though this system is more expensive to install, the Library has obtained State grant money and is expecting energy rebates from the New York State Energy Research Development Agency that will offset nearly 60% of the upfront costs. Combine that with the annual savings of $30,000 a year and the system will pay for itself in four years.
Stephen Hoefer, MBA
Manager of Operations & Finance
845-358-3370 x33

Friday, June 27, 2008
Pictures of the building project
The job starts by underpinning the Stevenson
House and building retaining wall.
Excavation for the cellar.
Great weather to construct footing forms.
Cellar walls are formed and filled with concrete.
5 feet of the existing Library was demolished.
Cellar floor and walls are complete.
Steel erection starts the end of May.
Steel for the 1st floor - Meeting & YA Rooms.
Steel decking on the 2nd level - Children's Room.
Steel for the 3rd level - Adult Reference.
Steel went up in about 3 weeks and cost $305,000.
Wednesday, May 7, 2008
May 7, 2008
In the past month the Library has awarded bids for the geothermal wells & exterior piping, sprinkler system, HVAC mechanicals, and plumbing. We have opened bids for roofing, are expecting the glass bids this week, door & hardware is out to bid now, and we anticipate the electrical bid will go out in approximately two weeks. We are pleased to report that in total, the bids awarded to date are slightly under our budgeted amount.
Exterior and interior finishes are being selected and refined. Just wait until you see how your library will look – MAGNIFICENT!
Stephen Hoefer, MBA
Manager of Operations & Finance
845-358-3370 x33
Tuesday, April 1, 2008
Waiting on Steel
In March we moved approximately 622 boxes containing 23,000 books and magazines to storage in the Village Hall basement. The Library would like to thank Mayor John Shields and the Village for supporting this project by providing storage space. As I write this update, temporary walls are being built on three floors in preparation of 5’ of the South wall to be removed – we apologize for any noise or inconvenience this may cause.
Stephen Hoefer, MBA
Manager of Operations & Finance 845-358-3370 x33
Tuesday, February 12, 2008
The Basement Walls Take Shape
Construction is progressing with the help of a mild winter so far. It took longer to excavate for the basement as we encountered red rock and had to hammer it loose – up to 7’ of rock in some spots. The new building is beginning to take shape as the basement concrete walls were poured on Friday February 8th.
Over the next few weeks you will see most of the activity take place inside the Library as we clear out the storage room and remove approximately 10,000 books in preparation for the South wall of the existing east wing being removed. Outside additional exterior column footings will be constructed and the new basement walls will be water-proofed and backfilled.
The Library has been hard at work designing the interior of the new building. So many decision regarding ceiling finishes, lighting fixtures, door hardware, security, telephone, floor finishes, elevator finishes, and numerous other choices have to be made – we are thankful for the many wonderful professionals who are there to guide us.
Stephen Hoefer, MBA
Manager of Operations & Finance
845-358-3370 x33
Thursday, December 20, 2007
THE NYACK LIBRARY CONSTRUCTION UPDATE
December 20, 2007
In the past few weeks construction has progressed with visible results:
The excavation contractor completed additional work on drainage lines and catch basins, and has been digging the cellar and removing dirt. The new cellar will be used to house mechanical equipment, heating systems and also provide room for general storage.
Once excavation is finished, the concrete crew will return to set the forms and pour the foundations for the new building. Weather permitting this should be completed within the next three weeks.
There will probably be a break in major activity during January while we wait for the steel to be manufactured. Then by mid-February steel erection will commence. At some point the south wall of the existing east wing will be removed and reconfigured to allow for a connecting corridor between the existing building and the new. This modification will require us to remove about 8,000 books (non-fiction and Reference) and place them in storage until the building is completed.
Yesterday we appeared before the Nyack Architectural Review Board and were granted an amendment to our plans to allow us to enclose three terraces on the corners of the upper level of the new building. We were concerned with safety and security issues, as well as additional insurance costs and the lost of floor space for seating and book materials. We thank the Board for their consideration.
Next update 1/7/08
Stephen Hoefer, MBA
Manager of Operations & Finance
845-358-3370 x33
Monday, December 3, 2007
12/03/07 Update
December 3, 2007
In the month of November our contractor had underpinned the Stevenson House (Klay Gallery & Art Café), partially graded the construction site, and installed some of the drainage system. The Library has been issued a building permit for concrete and steel work.
The elevator bid has been awarded and today the well for the elevator was drilled. In the next few week excavating and pouring of the concrete foundation will take place. Detailed architectural drawings progress and features of the interior design continues to be refined.
Steel is now expected to be delivered in February 2008 and a target of completing the new building around November 2008.
Next update 12/17/07
Stephen Hoefer, MBA
Manager of Operations & Finance
845-358-3370 x33
Thursday, October 18, 2007
The time has finally arrived - construction on the Library expansion will begin Monday, October 22, 2007.
- On Tuesday October 16th, The Nyack Library Board of Trustee’s approved the first three bids of excavation, concrete and steel. The Construction Manager has mobilized these trades and work begins on the long awaited library expansion.
- The current overall construction schedule is:
Excavation and concrete work completed late November 2007.
Steel is expected to be delivered and erected in January 2008.
Completion of the new building around September 2008.
Complete renovations to the existing building by January 2009.
- Construction fences will go up Monday to block off all access behind the Stevenson House (Klay Gallery & Art Café) to the parking lot and the back portion of the DePew House. For safety reasons only construction workers will be allowed on the construction site.
- By mid November the Library will be moving portions of the collection to off-site storage, rearrange remaining portions of the collections, and clear out 8’ from the south wall on three levels. It is the Library’s intention to have material that is stored off-site be available next business day.
Stephen Hoefer, MBA
Manager of Operations & Finance
Monday, September 24, 2007
Groundbreaking 1903
Groundbreaking Newsletter
http://nyack.lib.ny.us/Groundbreaking+newletter.pdf