Monday, December 3, 2007

12/03/07 Update

THE NYACK LIBRARY
December 3, 2007


In the month of November our contractor had underpinned the Stevenson House (Klay Gallery & Art Café), partially graded the construction site, and installed some of the drainage system. The Library has been issued a building permit for concrete and steel work.

The elevator bid has been awarded and today the well for the elevator was drilled. In the next few week excavating and pouring of the concrete foundation will take place. Detailed architectural drawings progress and features of the interior design continues to be refined.

Steel is now expected to be delivered in February 2008 and a target of completing the new building around November 2008.

Next update 12/17/07



Stephen Hoefer, MBA
Manager of Operations & Finance
845-358-3370 x33