May 7, 2008

On Monday, May 12th, we expect a crane and steel to be delivered. With this delivery you will see the construction site buzz with activity as the steel framing goes up and the steel decking goes down. It should take approximately 2-3 weeks for the iron workers to erect the skeleton of the building.

In the past month the Library has awarded bids for the geothermal wells & exterior piping, sprinkler system, HVAC mechanicals, and plumbing. We have opened bids for roofing, are expecting the glass bids this week, door & hardware is out to bid now, and we anticipate the electrical bid will go out in approximately two weeks. We are pleased to report that in total, the bids awarded to date are slightly under our budgeted amount.

Exterior and interior finishes are being selected and refined. Just wait until you see how your library will look – MAGNIFICENT!